I’ve had a lot of work this year and the weather at the weekends hasn’t always been good for garden wall building. But the wall is nearly at half height – there are already 1500 bricks in there and I budgeted around 3500 bricks for the whole wall.

The wall is high enough to backfill the trench and I’ll be sore tomorrow having moved many tons of earth. The wall looks a lot taller from the garden side now it is no longer hidden by big piles of earth.

There was some excess earth left over. I suppose there would be after putting 4m cube of concrete in the hole for the foundations. It was good exercise filling the skip.
I have a bag of top soil but it’s not accessible until the skip is collected. Also my wheelbarrow has a flat tyre. Grass seeding will have to wait.
